A facility assessment is a walk through of every major building system that records its condition, its remaining life and the cost to fix or replace it. Property managers use the result to plan repairs, set reserves and explain capital requests to owners. A good assessment ends with a ranked list of work and a dollar figure for each item.
This guide gives a system by system checklist, a simple rating scale, and a worked example that turns findings into a five year plan.
What a facility assessment covers
An assessment looks at the building as an asset. Routine inspections ask whether something works today. An assessment asks how long it will keep working and what it will cost when it stops. Plan one every three to five years for each building, and after a major event such as a flood or a change in use.
The checklist, system by system
Structure and envelope
- Foundation cracks, settlement and water at the base of walls.
- Exterior walls, sealants, windows and doors.
- Roof covering, flashing, drains and age. The guide on how often to inspect the roof and building envelope sets the routine between assessments.
Mechanical, electrical and plumbing
- Boilers, chillers, rooftop units and air handlers, with install year and service history.
- Electrical panels, switchgear and emergency lighting.
- Water heaters, piping, backflow devices and sewer lines.
Life safety and access
- Fire alarm, sprinklers, extinguishers and exit signs, with inspection dates.
- Elevators and their certificates.
- Accessible routes, ramps, parking and restrooms.
Life safety items follow their own legal schedules. Our life safety inspection schedule lists the usual intervals.
Site and common areas
- Paving, sidewalks, drainage and lighting.
- Lobbies, corridors, amenity rooms and signage.
Before the walk through
Preparation saves a second visit. Pull the last three years of work orders for the building, the equipment list with install years, warranty papers and any past assessment. Book access to roofs, mechanical rooms and a sample of units or suites. Tell tenants which days the team will be on site.
Split the building among two or three people by system, not by floor. One person rating every roof unit gives more consistent scores than three people rating some of each.
A rating scale your team will use the same way
Inconsistent ratings make an assessment useless. Use five levels and define each one:
| Rating | Meaning | Typical action |
|---|---|---|
| 5 Good | Working, early in its life | Routine maintenance |
| 4 Fair | Working, mid life | Watch, plan in 5+ years |
| 3 Worn | Working with repairs | Plan in 3 to 5 years |
| 2 Poor | Frequent failures | Replace in 1 to 2 years |
| 1 Failed | Not working or unsafe | Act now |
Record a photo, the install year, the expected life and a cost estimate for every item rated 3 or lower.
A worked example: turning findings into a plan
A fictional 96 unit apartment building has a replacement value of $12 million. The assessment finds these items rated 3 or lower:
| Item | Rating | Estimate | Year |
|---|---|---|---|
| Roof covering, 22 years old | 2 | $310,000 | 2027 |
| Two boilers, 19 years old | 3 | $140,000 | 2030 |
| Corridor carpet and paint | 3 | $55,000 | 2029 |
| Parking lot sealing and striping | 2 | $35,000 | 2027 |
Total needs are $540,000. Divided by the $12 million replacement value, that gives a facility condition index of 4.5%. The index is a quick way to compare buildings. A rising number year over year means repairs are falling behind.
The plan puts the roof and parking lot in 2027 at $345,000, the corridors in 2029 and the boilers in 2030, in line with the rating scale. The owner now sees a reserve need by year instead of one large ask. Work deferred from this list is covered in our guide to deferred maintenance.
Common mistakes
- Rating by eye with no install year or service history.
- Skipping spaces that are hard to reach, such as roofs, crawl spaces and mechanical rooms.
- Leaving the report as a PDF instead of creating planned work from it.
- Never updating it after repairs are done.
Your work order history is the best input for the next assessment. The post on using work order history for a capital plan shows how.
Where RIOO fits
RIOO keeps inspections, work orders and planned maintenance scheduling on NetSuite with property accounting. Assessment items can become planned tasks tied to the building, and repair costs post to the property's books, so the next assessment starts from real history.
Facility assessment questions
How often should a facility assessment be done?
Every three to five years is a common cycle, with updates after major repairs, damage or a change in use. Lenders and buyers may ask for one at sale or refinance.
Who should do a facility assessment?
Your own team can run the walk through with this checklist. Bring in licensed engineers for structure, roofs, elevators and major mechanical systems, or when a lender requires a third party report.
What is a facility condition index?
It is the cost of needed repairs divided by the building's replacement value. A lower number means a building in better shape.